Dave ThroupFlood defences are not the answer to future flooding, said a former Environment Agency (EA) worker.
In a thread on X, formerly Twitter, Dave Throup, who retired from the agency in 2021, said barriers would not be enough as climate change increased the frequency and ferocity of flooding.
Instead, he said, there needed to be natural flood management measures along the entire stretch of rivers.
The EA said it was developing a "broad range" of actions to tackle flooding.
Allow X content?
In his social media posts, Mr Throup said while many communities along the rivers Severn and Wye were protected by barriers, they were giving a "false sense of security".
Floods, he said, were getting bigger due to a rapidly changing climate and, in 2020, every flood defence on the Severn and Wye had been within a metre of overtopping.
Getty Images
Dave ThroupWith predictions showing "very significant increases" in river levels, he said there needed to be catchment-wide plans to use natural methods such as planting, ponds and bogs which can slow the flow of rivers.
Reducing the severity of flooding by lowering out the flood peak as it passes along a river is known as attenuation, and works by spreading out the drainage of a river along its catchment.
Mr Throup's comments were widely shared on X, including by journalist Caitlin Moran.
Getty Images Currently, Bewdley, Upton-on-Severn, Shrewsbury and Ironbridge have defences.
Beales Corner, the opposite side of the current permanent defences in Bewdley, is getting its own permanent protection, with Severn Stoke in Worcestershire also getting its own barriers.

However, the barriers have not been built quickly enough in Severn Stoke and its residents flooded again last week.
Asked by BBC Hereford & Worcester about the delayed construction, Harriett Baldwin, West Worcestershire MP, said the project had planning permission and funding but was "frustratingly" delayed when the Environment Agency failed to come to an agreement with a contractor.
UK ParliamentThe Tory MP said the scheme was a "top priority" for her, adding she would meet with the EA about the issue.
"It will get done. I will not give up. I have been working on this for 10 years. It will get done," she said.
The EA said it had paused earthworks until the spring, pending the agreement of an affordable price with a supplier and that affordability of the scheme was a "key challenge" but it had not given up.
Getty ImagesIn response to questions about future flood preparedness, the EA said: "We work tirelessly to protect communities from the threat of flooding, maintaining approximately 76,000 flood assets across England.
"It is thanks to this work we have protected more than 75,000 properties from flooding caused by Storm Henk."
It said it was "essential" communities got ready for the impacts of climate change by becoming more resilient as a nation.
"That is why creating climate-resilient places lies at the heart of our flood strategy; ensuring we embrace a broad range of resilience actions to make us better prepared, such as £200m to test and develop new ways to create a nation resilient to flooding and coastal change," the EA added.

Follow BBC West Midlands on Facebook, X and Instagram. Send your story ideas to: [email protected]