Second nuclear reactor arrives at Hinkley Point C

Dan AyersSomerset
News imageEDF A huge white, orange and yellow cylinder reactor is being transported on a wide lorry base in the foreground. Two people in orange high-visibility clothes guide it along the route. There's a narrow road leading up to the Hinkley Point C construction site in the background, which is filled with dozens of cranes and has two central domes.EDF
The reactor was shipped to the UK from France before being transported to Hinkley Point C power station by barge before a final journey on the road

The second nuclear reactor has arrived at Britain's newest nuclear power station, which is due to open in 2031.

EDF said the twin nuclear power station at Hinkley Point C in Somerset now has its second high-strength steel cylinder, which weighs 500 tonnes and is 13m (42ft) long.

The reactor was shipped from France to Avonmouth Docks in Bristol and was then transported by barge to Combwich Wharf on the River Parrett before a six-hour road trip by transporter for the final four miles (6km) to the site.

The first nuclear reactor arrived in 2023, with the cylinders designed to use a pressure vessel to harness nuclear fission to make heat and steam to power the world's largest turbines.

When the site is operational, each of the reactors - known as Unit 1 and Unit 2 - will power about three million homes around the clock.

EDF said the delivery of the second reactor pressure vessel was a major moment in Hinkley Point C's construction.

Claire Warner-Blackman, freight and marine area manager, said: "Months of planning and exceptional teamwork has resulted in the successful delivery of this critical component to Hinkley Point C.

"The Reactor Pressure Vessel sits at the heart of the nuclear power station and so it is vital to ensure that delivery goes without a hitch.

"I'm very proud to have been part of this complex operation and my thanks go to all of the brilliant teams involved."

News imageEDF Drone style photo of a boat with the huge cylinder reactor on it. It is dark and there's a bright light shining on the reactor and around it. On the horizon bright lights can be seen on the construction site, including lit-up cranes.EDF
EDF said the reactor's arrival was a major moment for the project

EDF said Unit 1 has been welded into place with work continuing to fit pipes, cables and equipment. It said the focus at Unit 2 is on completing its buildings following a successful dome lift.

Construction at the site is due to reach its peak in the next 18 months, with about 15,000 people expected to work on the build.

The estimated cost of the project has risen to £46bn from the £18bn predicted in 2017.

News imageEDF A cylinder reactor which is as tall as a two-storey home next to it is being transported along a road in rural Somerset. The transporter takes up both lanes of the road.EDF
It took six hours to transport the reactor along roads in West Somerset

Follow BBC Somerset on Facebook and X. Send your story ideas to us on email or via WhatsApp on 0800 313 4630.


More from the BBC