 Bewdley has flooded several times in recent years |
Work has begun on the second phase of a new flood defence scheme for the south side of Bewdley. The �7m project will extend the length of the defences from Bewdley Bridge to the town's cricket ground.
The same invisible flood defence system used to protect the north side of the town will be used.
It is hoped that the extension of the scheme will offer protection to around 175 extra properties.
Project manager Roger Prestwood said: "It is important to the long-term prospects of Bewdley to protect the town from the disruption and distress caused by flooding.
"We recognise that there will be some short-term impact, but we will do all we can to keep this to a minimum and we ask people for their understanding while we work to protect their town."
Bewdley has been hit by several floods, including the worst in more than 50 years in November 2000.
Around 450 metres of demountable flood defence and 140 metres of permanent brick-faced wall will be used,
Worcestershire's innovative flood defence system combines extensive underground defences and drainage pipes with a portable aluminium barrier.
The scheme, funded by a grant from the Department for Environment, Food and Rural Affairs (Defra), should be completed by the end of 2005.