Poor weather has disrupted building work on the runway extension project at the Isle of Man airport. Strong winds and stormy seas have delayed the off-loading of giant rock armour being shipped from Norway to Ronaldsway Airport in Ballasalla. The current works form part of a construction project valued at nearly £44m and should be completed by the end of the year. An airport spokeswoman said the current works had overrun by 10 days.
|